Elevator Backup: UPS, ARD and Rescue Circuit

How elevator backup works: UPS vs ARD rescue device vs generator, how to size the rescue circuit, and what to confirm with the lift contractor.

HENGLAN Engineering Team Power systems engineering 5 min read Published Updated
Hotel building with passenger lifts served by a backup power system
TL;DR

An elevator does not keep running on a UPS during an outage in most buildings. The AD-ARD rescue device takes over, drives the car to the nearest landing and opens the doors, drawing 7.5–30 kW depending on the motor. Size it on the lift motor and the rescue cycle, and confirm the interface with the lift contractor.

An elevator is not a normal backup load. It has a motor with a high starting current, a controller that must stay alive, a rescue sequence defined by the lift code, and a machine room that is often hot and small. A generic UPS quote rarely covers all four.

This guide explains the three backup layers, how to size the rescue circuit, and what the lift contractor and the power supplier must agree before the order.

What happens to a lift when the power fails?

A lift with a variable-frequency drive stops when the DC bus collapses. The passengers are inside the car, the controller may still be alive for a few seconds, and the brake sets. The rescue sequence then depends on the equipment installed:

  • ARD (automatic rescue device): an internal battery and inverter move the car to the nearest floor and open the doors once.
  • UPS on the controller: keeps the controller, door operator, communications and rescue circuit powered, but does not move the car unless the drive is also backed up.
  • Generator: supplies the whole lift after 10–30 seconds, but the gap is exactly when the rescue is needed.

The practical design is usually a combination: the ARD handles the one-time rescue, a small UPS keeps the controller and communications alive, and the generator takes over for normal service.

UPS, ARD or generator: which layer do you need?

The three layers solve different problems and should not be substituted for one another.

LayerWhat it powersRuntimeTypical use
ARDCar movement to the nearest floorOne rescue cycleEvery passenger lift
UPSController, doors, intercom, rescue circuit15–60 minutesHigh-rise, hospital, hotel
GeneratorWhole lift and buildingHoursLong outages, fire service lift

If the building has a generator, the UPS only needs to cover the generator start and the rescue. If there is no generator, the ARD is the primary rescue path and the UPS is optional for the controller.

How do you size the elevator UPS?

Start with the load list from the lift contractor. The controller nameplate is only part of the load.

  1. Controller and drive control: typically 0.5–2 kVA.
  2. Door operator and lighting: 0.3–1 kVA.
  3. Intercom, CCTV and emergency lighting: 0.2–0.5 kVA.
  4. Rescue circuit and brake release: per the lift manufacturer.
  5. Design margin: add 25% for ageing, temperature and future load.

For a 2 kVA continuous load with 30 minutes of runtime at a 192 VDC bus, 0.85 inverter efficiency and 0.6 usable depth of discharge, the estimate is about 39 Ah. A 40–50 Ah bank or a 24 V lithium module covers it with margin. Confirm the charger current and the battery room before fixing the model.

BuildingController + rescue loadUPS sizeRuntime
6–10 floor office1–2 kVA2–3 kVA15–30 min
Hotel, 12–20 floors2–4 kVA3–6 kVA30–60 min
Hospital, fire-service lift3–8 kVA6–10 kVA60–120 min
High-rise, two cars4–10 kVA10–20 kVA30–60 min

Can the UPS run the motor?

Usually not, and it should not be forced. A standard IT UPS is designed for a nonlinear electronic load, not for a motor with a 5–7 times starting current. A dedicated elevator UPS or a drive-rated inverter is different: it is sized for the motor, the starting method and the regenerative energy.

If the project needs the car to run on battery, use a lift drive that supports a battery input, a bidirectional converter or a braking resistor, and a UPS rated for the motor’s starting current. Confirm the drive manufacturer’s DC bus voltage and the UPS output configuration. A mismatch here is expensive and dangerous.

What should be in the specification?

A lift backup specification should state:

  • The rescue strategy: ARD, UPS, generator or a combination.
  • The load list and the runtime for each layer.
  • The input voltage, phase and frequency (230 V / 400 V, 50 Hz or 220 V / 60 Hz).
  • The battery chemistry and the machine-room temperature.
  • The communication interface to the building management system (dry contact, RS485, MODBUS, SNMP).
  • The test and handover procedure with the lift contractor.

Do not accept a quotation that lists only “elevator UPS 3 kVA”. The rescue circuit, the door operator and the battery room decide whether the system works on the day.

How does the battery room affect the design?

A lift machine room is often the hottest room in the building. VRLA life halves for roughly every 10 °C above 25 °C, so a 35 °C room turns a 10-year block into a 5-year block. LiFePO4 has a wider operating window and a longer cycle life, but it still needs ventilation and a BMS rated for the ambient.

If the room cannot be cooled, derate the battery and shorten the replacement interval. If the room is small, a rack or wall-mounted lithium module may fit where a lead-acid string does not.

Which standards and documents apply?

The lift is covered by EN 81-20 / EN 81-50 in Europe and ASME A17.1 / CSA B44 in North America, plus local rescue and emergency-power rules. The UPS is specified to IEC 62040-1/-2/-3, and the battery to IEC 60896-21/-22 for VRLA or IEC 62619 for lithium. A fire-service lift usually has an additional fire-rated supply requirement.

Ask for the model datasheet, the battery configuration sheet, the test report and the interface drawing. The lift contractor should confirm the rescue sequence and the load list in writing before the UPS is ordered.

Next step

Send the controller nameplate, the rescue load, the number of floors, the machine-room temperature and the required runtime. We will return the UPS size, the battery configuration and the interface list for the lift contractor.

Start with the elevator UPS product page, compare the three-phase UPS range for a high-rise, or use the sizing calculator for a first estimate.

FAQ

Questions from project buyers.

Project-specific answers. If your question is not here, send the load list and the site conditions.

Talk to an engineer

Does an elevator need a UPS or an ARD?

They do different jobs. An ARD (automatic rescue device) moves the car to the nearest floor and opens the doors once after a power failure. A UPS keeps the lift controller and the rescue circuit powered for a defined time, and can support repeated rescue cycles. Some projects use both: the ARD for the one-time rescue, the UPS for the controller, communications and the second cycle.

How long should an elevator UPS run?

The usual target is 15–30 minutes for the controller and the rescue circuit, enough for one or two rescue cycles and for the generator to start. The motor itself is not normally carried by the UPS; the car is moved by the ARD or by the generator-backed drive.

Can a UPS run the elevator motor?

Only a dedicated elevator UPS or a drive-rated inverter sized for the motor starting current can run the motor. A standard IT UPS cannot. Lifting a fully loaded car needs a high starting current and a regenerative drive may push energy back to the DC bus, so the converter must be bidirectional or have a braking resistor.

What size UPS does a lift controller need?

Most controllers draw 1–3 kVA, but the rescue circuit, door operator, lighting and communications add load. Start from the controller nameplate and the lift contractor's rescue load, add 25% margin, and confirm the runtime with the battery manufacturer's discharge curve.

Which standards apply?

EN 81-20 and EN 81-50 cover lift safety and testing in Europe; ASME A17.1/CSA B44 is common in North America; local codes add rescue and emergency power requirements. The UPS itself is specified to IEC 62040-1/-2/-3, and the battery to IEC 60896 or IEC 62619.

Does the battery room matter?

Yes. A lift machine room is often hot and has limited space. VRLA blocks lose life above 30 °C; LiFePO4 needs ventilation and a BMS rated for the ambient. Confirm the room temperature before selecting the battery.

Next step

Send the load list. We will return the configuration.

Tell us the kW, the backup time, the phase, and the site country. You will get a capacity recommendation, a battery configuration, and the model sheet.

  • Capacity and topology recommendation
  • Battery bank and runtime estimate
  • Model sheet and commercial offer

Request a configuration and quotation

Send the load list, backup time, and site conditions. We will return a capacity recommendation, battery configuration, and commercial offer.

By submitting this form you agree to our privacy policy. Privacy policy