Skip to content
Large capacity

Large-capacity UPS: 20–200 kVA for facilities and data centers.

Large UPS frames from 20 to 200 kVA with parallel options, 384 VDC battery banks, 0 ms transfer and project support for data centers and plants.

Large capacity UPS cabinets
Frame range
20–200 kVA
Battery bus
384 VDC
Parallel units
Up to 6
Transfer
0 ms
TL;DR

Above 20 kVA, the UPS becomes a project item. The frame, battery, bypass, switchgear, cable, cooling, and floor loading are all part of the design. A 200 kVA UPS can weigh more than a small car with its battery bank, and the room must be planned before the equipment arrives.

The 20–200 kVA range covers small and medium data centers, hospitals, telecom core sites, commercial buildings, and industrial plants. The choice between a monolithic frame and a modular frame depends on the redundancy target, the growth plan, and the available floor space.

Monolithic or modular large UPS?

A monolithic frame is simpler and often lower cost for a fixed load. A modular frame is better when the load will grow in phases or when N+1 redundancy must be maintained without a full parallel system. For a 200 kW data center with a phased fit-out, modular is usually the better lifecycle choice.

For a plant with a stable load and a single large frame, a monolithic 100–200 kVA UPS with an external maintenance bypass is straightforward and easy to service.

How big is the battery bank for 2 hours?

A 100 kVA UPS at 80% load and 0.9 PF draws 72 kW. For 2 hours, the usable energy is about 144 kWh; at 80% depth of discharge, the nominal bank is about 180 kWh. At 384 VDC, that is roughly 470 Ah, or five 100 Ah strings of 32 blocks. The battery room, floor loading, and ventilation become major design items.

For long runtime, lithium can reduce the footprint and weight, but the UPS charger and BMS must be compatible. Do not assume a lead-acid charger can charge a lithium bank safely.

Large UPS battery examples at 80% load

UPSLoadRuntimeNominal energyApprox. 12 V 100 Ah blocks
20 kVA14.4 kW1 h18 kWh32 blocks (1 string)
60 kVA43.2 kW1 h54 kWh64 blocks (2 strings)
100 kVA72 kW1 h90 kWh96 blocks (3 strings)
100 kVA72 kW2 h180 kWh160 blocks (5 strings)
200 kVA144 kW1 h180 kWh160 blocks (5 strings)

Indicative only. Final sizing must use the battery discharge curve, end voltage, temperature, and charger limit.

What does the UPS room need?

  • Floor loading for the UPS and battery cabinets
  • Maintenance clearance at the front and rear
  • Cooling for the UPS losses and battery recharge
  • Ventilation for the battery room
  • Fire detection and suppression per local code
  • Cable entry and bend radius for the input/output cables
  • A maintenance bypass and upstream protection
  • Access route for delivery and future replacement
Standards & documents

Which standards and documents are referenced on this page?

The table lists the model-specific standards and conformity documents a project buyer should ask for. Availability depends on the frame, the battery, and the destination market; request the document that names your model.

UPS standards and documents

ReferenceWhat it covers
IEC 62040-1UPS general and safety requirements
IEC 62040-2UPS electromagnetic compatibility (EMC)
IEC 62040-3UPS performance and test requirements
IEC 60896-21 / -22VRLA stationary battery type and performance tests
IEC 62619Safety of lithium cells and batteries for industrial use
UN38.3 / MSDSLithium battery transport test and material safety data
CE / RoHSEU conformity and restricted-substance declaration
ISO 9001Manufacturing quality management system
SNMP / MODBUSRemote monitoring and BMS interface
IP20 / IP21Cabinet ingress protection for indoor installation

Certificates are issued against the exact model and configuration. See the certifications page for how to confirm scope and revision, or send the model to request the current document.

Project checklists

Confirm the inputs and documents before quoting.

Project inputs to confirm

ItemWhat to confirmWhy it matters
LoadRunning kW, largest motor, load stepSets kVA, overload and topology
RuntimeMinutes, generator availability, battery roomSets battery bank and charger
SupplyVoltage, frequency, phase, input currentSets model, breaker and cable
SiteCountry, altitude, ambient temperature, dustSets derating, IP and documents
BatteryVRLA, LiFePO4, footprint, weight limitSets chemistry and room layout
DocumentationConformity route, test report, languageSets document package and lead time
FAQ

Questions from project buyers.

Project-specific answers. If your question is not here, send the load list and the site conditions.

Talk to an engineer

How much floor space does a 200 kVA UPS need?

The UPS frame is about 705 × 1,051 × 1,646 mm, but the battery cabinets and maintenance clearance can triple the footprint. Plan the room from the layout drawing, not from the UPS dimensions alone.

Can I install a large UPS on an upper floor?

Only after a structural check. A 200 kVA UPS with a 1-hour battery bank can weigh several tonnes. The floor loading, the access route, and the lifting equipment must be confirmed.

Should I use a shared battery bank for parallel UPS?

Shared battery is possible on selected frames, but it requires careful protection coordination and a common DC bus design. Separate battery banks are simpler and isolate a fault to one UPS.

How long does a large UPS project take?

Lead time depends on the frame, battery, and documentation. The project schedule should include approval drawings, battery room preparation, delivery, installation, commissioning, and load testing.

Do you provide a single-line diagram?

Yes, for project orders we provide the UPS single-line diagram, terminal details, and battery configuration. The upstream switchgear and bypass are coordinated with the local electrical contractor.

Next step

Send the load list. We will return the configuration.

Tell us the kW, the backup time, the phase, and the site country. You will get a capacity recommendation, a battery configuration, and the model sheet.

  • Capacity and topology recommendation
  • Battery bank and runtime estimate
  • Model sheet and commercial offer

Request a configuration and quotation

Send the load list, backup time, and site conditions. We will return a capacity recommendation, battery configuration, and commercial offer.

By submitting this form you agree to our privacy policy. Privacy policy

Published Last updated Specifications and certification are confirmed per project.